Substation Scout

Loving, TX interconnection queue

2 active projects totalling 244.3 MW in the ERCOT queue.

2active projects
244.3active MW
2total filed
Queue IDProjectkVMWResourceStatus
30INR0099 Quadspring BESS 138 200.7 Battery SS Started, FIS Started, No IA
26INR0529 Electric E - West Texas Generation 138 43.6 Gas SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.