Substation Scout

Rosharon BESS

ERCOT queue ID 26INR0497

Rosharon BESS (26INR0497) is listed in the ERCOT interconnection queue as a 120 MW battery project in Brazoria County, TX. The filing names Archer (ACH) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, No IA”, with a target commercial operation date of June 30, 2028. It records the screening study as complete on July 5, 2024 and the full interconnection study as approved on January 14, 2026.

Queue ID26INR0497
Project nameRosharon BESS
Status (as published)SS Completed, FIS Completed, No IA
SubstationArcher (ACH)
Point of interconnection138 kV 42570 Archer (ACH)
CountyBrazoria
StateTX
Voltage138 kV
Capacity120 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-06-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Brazoria, TX: 63 requests in the ERCOT queue, 54 active totaling 10,984.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityRosharon BESS LLC
CDR reporting zoneCOASTAL
Fuel codeOTH
Technology codeBA
Screening study complete2024-07-05
Full interconnection study approved2026-01-14

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first