Rio Hondo BESS

ERCOT queue ID 26INR0461

Rio Hondo BESS (26INR0461) is listed in the ERCOT interconnection queue as a 200.8 MW battery project in Cameron County, TX. The filing names Tap # Las Pulgas - # Rio Hondo as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of June 30, 2028. It records the screening study as complete on August 5, 2024.

Queue ID26INR0461
Project nameRio Hondo BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationTap # Las Pulgas - # Rio Hondo
Point of interconnectionTap 138kV #80309 Las Pulgas - #8319 Rio Hondo
CountyCameron
StateTX
Voltage138 kV
Capacity200.8 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-06-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Cameron, TX: 32 requests in the ERCOT queue, 30 active totaling 8,649.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entitySBESS TX25 LLC
CDR reporting zoneCOASTAL
Fuel codeOTH
Technology codeBA
Screening study complete2024-08-05

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.