GAMAY ENERGY STORAGE
ERCOT queue ID 26INR0417
GAMAY ENERGY STORAGE (26INR0417) is listed in the ERCOT interconnection queue as a 418.6 MW battery project in Brazoria County, TX. The filing names Tap Line from TNFM524 to West Columbia Main, in Brazoria County. as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of January 1, 2028. It records the screening study as complete on April 30, 2024 and the interconnection agreement as signed on May 27, 2025.
| Queue ID | 26INR0417 |
|---|---|
| Project name | GAMAY ENERGY STORAGE |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap Line from TNFM524 to West Columbia Main, in Brazoria County. |
| Point of interconnection | Tap 138 kV Line from TNFM524 (39703) to West Columbia Main (39500), in Brazoria County. |
| County | Brazoria |
| State | TX |
| Voltage | 138 kV |
| Capacity | 418.6 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-01-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Brazoria, TX: 63 requests in the ERCOT queue, 54 active totaling 10,984.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | GAMAY ENERGY STORAGE LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2025-05-27 |
| Screening study complete | 2024-04-30 |
| Air permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.