Sherbino II BESS SLF (26INR0296) is listed in the ERCOT interconnection queue as a 77.4 MW battery project in Pecos County, TX. The filing names TNMP White baker Switching Station as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of April 18, 2028. It records the screening study as complete on February 27, 2024, the full interconnection study as approved on April 23, 2025 and the interconnection agreement as signed on August 1, 2024.

Queue ID26INR0296
Project nameSherbino II BESS SLF
Status (as published)SS Completed, FIS Completed, IA
SubstationTNMP White baker Switching Station
Point of interconnection38430 TNMP White baker Switching Station 138kV
CountyPecos
StateTX
Voltage138 kV
Capacity77.4 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-04-18
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Pecos, TX: 63 requests in the ERCOT queue, 58 active totaling 21,379.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityPhoenix Battery Storage, LLC
CDR reporting zoneWEST
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2024-08-01
Screening study complete2024-02-27
Full interconnection study approved2025-04-23

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first