Substation Scout

Momentum Hazy Jane BESS

ERCOT queue ID 26INR0273

Queue ID26INR0273
Project nameMomentum Hazy Jane BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Judkins - Edward
Point of interconnectionTap 138kV 1102 Judkins - 1110 Edward
CountyEctor
StateTX
Voltage138 kV
Capacity125.5 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-02-26
Source datasetlarge

Additional filed fields

Interconnecting EntityMOMENTUM HAZY JANE, LLC
Cdr ZoneWEST
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45331

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.