Bastrop Peaking Generators (TEF-Due Diligence)
ERCOT queue ID 26INR0261
| Queue ID | 26INR0261 |
|---|---|
| Project name | Bastrop Peaking Generators (TEF-Due Diligence) |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | L_GARFIE5_1Y |
| Point of interconnection | 7048 L_GARFIE5_1Y 345kV |
| County | Bastrop |
| State | TX |
| Voltage | 345 kV |
| Capacity | 1,104 MW |
| Resource (as published) | GAS/GT |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2027-12-07 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | MPH Bastrop Peakers, LLC |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | GAS |
| Technology Code | GT |
| Ia Signed | 46010 |
| Screening Study Complete | 45413 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.