Bastrop Peaking Generators (TEF-Due Diligence)
ERCOT queue ID 26INR0261
Bastrop Peaking Generators (TEF-Due Diligence) (26INR0261) is listed in the ERCOT interconnection queue as a 1,104 MW gas project in Bastrop County, TX. The filing names L_GARFIE5_1Y as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of December 7, 2027. It records the screening study as complete on May 1, 2024 and the interconnection agreement as signed on December 19, 2025.
| Queue ID | 26INR0261 |
|---|---|
| Project name | Bastrop Peaking Generators (TEF-Due Diligence) |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | L_GARFIE5_1Y |
| Point of interconnection | 7048 L_GARFIE5_1Y 345kV |
| County | Bastrop |
| State | TX |
| Voltage | 345 kV |
| Capacity | 1,104 MW |
| Resource (as published) | GAS/GT |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2027-12-07 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Bastrop, TX: 16 requests in the ERCOT queue, 14 active totaling 5,098.7 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | MPH Bastrop Peakers, LLC |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | GAS |
| Technology code | GT |
| Interconnection agreement signed | 2025-12-19 |
| Screening study complete | 2024-05-01 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.