| Queue ID | 26INR0260 |
|---|---|
| Project name | Evans Creek Energy Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Comstock Substation (PSSE Bus #) |
| Point of interconnection | Comstock 138kV Substation (PSSE Bus #8683) |
| County | Val Verde |
| State | TX |
| Voltage | 138 kV |
| Capacity | 103 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2028-04-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Evans Creek Energy Storage LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 45313 |