Substation Scout

Skipjack Energy Storage

ERCOT queue ID 26INR0189

Skipjack Energy Storage (26INR0189) is listed in the ERCOT interconnection queue as a 150.6 MW battery project in Brazoria County, TX. The filing names Tap 138 Nash - W A Parish ckt #2 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of February 28, 2028. It records the screening study as complete on October 27, 2023 and the interconnection agreement as signed on August 13, 2024.

Queue ID26INR0189
Project nameSkipjack Energy Storage
Status (as published)SS Completed, FIS Started, IA
SubstationTap 138 Nash - W A Parish ckt #2
Point of interconnectionTap 138 42980 Nash - 44010 W A Parish ckt #2
CountyBrazoria
StateTX
VoltageNot reported
Capacity150.6 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-02-28
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Brazoria, TX: 63 requests in the ERCOT queue, 54 active totaling 10,984.8 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entitySkipper Energy Storage LLC
CDR reporting zoneCOASTAL
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2024-08-13
Screening study complete2023-10-27

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.