Substation Scout

Wichita Falls Energy Storage

ERCOT queue ID 25INR0628

Queue ID25INR0628
Project nameWichita Falls Energy Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Bowman - Cobb Switch
Point of interconnectionTap 345kV 1422 Bowman - 1458 Cobb Switch
CountyArcher
StateTX
Voltage345 kV
Capacity202 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-08-01
Source datasetlarge

Additional filed fields

Interconnecting EntityWichita Falls Energy Storage LLC
Cdr ZoneWEST
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45437
Air PermitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.