Substation Scout

Hockley BESS

ERCOT queue ID 25INR0602

Hockley BESS (25INR0602) is listed in the ERCOT interconnection queue as a 10 MW battery project in Harris County, TX. The filing names 30., -95. Station Name (Station Code): Hockley (HK) LONG CODE: HOCKLY Short Code: HK TR5 ERCOT Bus Name: Hockley Feeder: HK-91 ERCOT Load Name: TR5 CNP XFMR #: HK TR5 ERCOT Bus #: Node as its point of interconnection. ERCOT lists its status as “In Queue”, with a target commercial operation date of March 1, 2027. It records the interconnection agreement as signed on April 29, 2024.

Queue ID25INR0602
Project nameHockley BESS
Status (as published)In Queue
Substation30., -95. Station Name (Station Code): Hockley (HK) LONG CODE: HOCKLY Short Code: HK TR5 ERCOT Bus Name: Hockley Feeder: HK-91 ERCOT Load Name: TR5 CNP XFMR #: HK TR5 ERCOT Bus #: Node
Point of interconnection30.021619, -95.846315 Station Name (Station Code): Hockley (HK) LONG CODE: HOCKLY Short Code: HK TR5 ERCOT Bus Name: Hockley Feeder: HK-91 ERCOT Load Name: TR5 CNP XFMR #: HK TR5 ERCOT Bus #: 45880 Node: 0101
CountyHarris
StateTX
VoltageNot reported
Capacity10 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2027-03-01
Source datasetsmall

Same substation and county

Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityRegis Hockley LLC
CDR reporting zoneHOUSTON
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2024-04-29

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.