Substation Scout

Copano Bay Energy Storage

ERCOT queue ID 25INR0566

Queue ID25INR0566
Project nameCopano Bay Energy Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Nash - WA Parish Ckt 2
Point of interconnectionTap 138kV 42980 Nash - 44010 WA Parish Ckt 2
CountyBrazoria
StateTX
Voltage138 kV
Capacity201 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityCopano Bay Energy Storage, LLC
Cdr ZoneCOASTAL
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45313
Air PermitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.