Copano Bay Energy Storage (25INR0566) is listed in the ERCOT interconnection queue as a 201 MW battery project in Brazoria County, TX. The filing names Tap Nash - WA Parish Ckt 2 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2028. It records the screening study as complete on January 22, 2024.
| Queue ID | 25INR0566 |
|---|---|
| Project name | Copano Bay Energy Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Nash - WA Parish Ckt 2 |
| Point of interconnection | Tap 138kV 42980 Nash - 44010 WA Parish Ckt 2 |
| County | Brazoria |
| State | TX |
| Voltage | 138 kV |
| Capacity | 201 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-12-31 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Brazoria, TX: 63 requests in the ERCOT queue, 54 active totaling 10,984.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Copano Bay Energy Storage, LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2024-01-22 |
| Air permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.