Vault Solar
ERCOT queue ID 25INR0482
| Queue ID | 25INR0482 |
|---|---|
| Project name | Vault Solar |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap #331 Rwmiller - #320 Jaybird |
| Point of interconnection | Tap #331 Rwmiller - #320 Jaybird 138kV |
| County | Palo Pinto |
| State | TX |
| Voltage | 138 kV |
| Capacity | 108.5 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2027-12-31 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | PPM THR Solar |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Ia Signed | 46203 |
| Screening Study Complete | 45189 |
| Fis Approved | 45628 |
| Water Availability | Not Required |