Bell Creek BESS
ERCOT queue ID 25INR0480
Bell Creek BESS (25INR0480) is listed in the ERCOT interconnection queue as a 200.9 MW battery project in Brazoria County, TX. The filing names Tap West Colombia - FM524 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of October 30, 2027. It records the screening study as complete on September 21, 2023, the full interconnection study as approved on May 16, 2024 and the interconnection agreement as signed on November 14, 2024.
| Queue ID | 25INR0480 |
|---|---|
| Project name | Bell Creek BESS |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap West Colombia - FM524 |
| Point of interconnection | Tap 138kV 39500 West Colombia - 39703 FM524 |
| County | Brazoria |
| State | TX |
| Voltage | 138 kV |
| Capacity | 200.9 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2027-10-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Brazoria, TX: 63 requests in the ERCOT queue, 54 active totaling 10,984.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | BELL CREEK BESS, LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2024-11-14 |
| Screening study complete | 2023-09-21 |
| Full interconnection study approved | 2024-05-16 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.