Houston BESS
ERCOT queue ID 25INR0420
Houston BESS (25INR0420) is listed in the ERCOT interconnection queue as a 227.9 MW battery project in Harris County, TX. The filing names Tap LAUDER (#) - RITTENHOUSE (#) ckt 95 as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, No IA”, with a target commercial operation date of January 1, 2028. It records the screening study as complete on July 3, 2023 and the full interconnection study as approved on April 4, 2024.
| Queue ID | 25INR0420 |
|---|---|
| Project name | Houston BESS |
| Status (as published) | SS Completed, FIS Completed, No IA |
| Substation | Tap LAUDER (#) - RITTENHOUSE (#) ckt 95 |
| Point of interconnection | Tap 138 kV LAUDER (#46002) - RITTENHOUSE (#46282) ckt 95 |
| County | Harris |
| State | TX |
| Voltage | 138 kV |
| Capacity | 227.9 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-01-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | SMT Houston |
|---|---|
| CDR reporting zone | HOUSTON |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2023-07-03 |
| Full interconnection study approved | 2024-04-04 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.