Substation Scout

Red Top Solar I

ERCOT queue ID 25INR0306

Queue ID25INR0306
Project nameRed Top Solar I
Status (as published)SS Completed, FIS Completed, No IA
SubstationTap Graham SES - Short Grass
Point of interconnectionTap 138kV 1431 Graham SES - Short Grass 11525
CountyYoung
StateTX
Voltage138 kV
Capacity200.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-11-30
Source datasetlarge

Additional filed fields

Interconnecting EntityCat Red Top Solar, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45030
Fis Approved46029
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.