Substation Scout

Young, TX interconnection queue

8 active projects totalling 2,177.5 MW in the ERCOT queue, plus 3 with terminal status (shown greyed).

8active projects
2,177.5active MW
11total filed
Queue IDProjectkVMWResourceStatus
29INR0204 Miller Bend Energy BESS 345 547.7 Battery SS Completed, FIS Started, No IA
29INR0203 Miller Bend Energy Solar 345 531.8 Solar SS Completed, FIS Started, No IA
29INR0172 Sweetheart BESS 345 310.2 Battery SS Completed, FIS Started, No IA
28INR0194 Tapaderos Solar n/r 301.6 Solar Inactive
29INR0171 Sweetheart Solar 345 301.1 Solar SS Completed, FIS Started, No IA
29INR0084 Jolly Rock Storage Center 138 208.6 Battery SS Completed, FIS Started, No IA
28INR0196 Tapaderos Storage n/r 207 Battery Inactive
25INR0306 Red Top Solar I 138 200.6 Solar SS Completed, FIS Completed, No IA
24INR0507 Young Wind II SLF n/r 152.3 Wind Inactive
26INR0302 Young County Energy Storage 138 104.5 Battery SS Completed, FIS Completed, No IA
20INR0019 Trinity Hills Wind repower 345 -27 Wind SS Completed, FIS Completed, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.