Savannah Oaks Solar

ERCOT queue ID 25INR0286

Queue ID25INR0286
Project nameSavannah Oaks Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Limestone Plant - 967 Gibbons Creek
Point of interconnectionTap 345kV 46020 Limestone Plant - 967 Gibbons Creek
CountyMadison
StateTX
Voltage345 kV
Capacity201.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-09-30
Source datasetlarge

Additional filed fields

Interconnecting EntitySavannah Oaks Solar Project LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45015
Water AvailabilityNot Required