Harryoung Solar
ERCOT queue ID 25INR0270
Harryoung Solar (25INR0270) is listed in the ERCOT interconnection queue as a 190 MW solar project in Cameron County, TX. The filing names Tap Rio Hondo - SOUTH SANTA ROSA as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of May 15, 2028. It records the screening study as complete on February 17, 2023.
| Queue ID | 25INR0270 |
|---|---|
| Project name | Harryoung Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Rio Hondo - SOUTH SANTA ROSA |
| Point of interconnection | Tap 8319 Rio Hondo - SOUTH SANTA ROSA: 8359, 138kV |
| County | Cameron |
| State | TX |
| Voltage | 138 kV |
| Capacity | 190 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-05-15 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Cameron, TX: 32 requests in the ERCOT queue, 30 active totaling 8,649.9 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Gransolar Texas Four LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | SOL |
| Technology code | PV |
| Screening study complete | 2023-02-17 |
| Air permit | Not Required |
| Water availability | Not Required |