August Draw Solar
ERCOT queue ID 25INR0112
August Draw Solar (25INR0112) is listed in the ERCOT interconnection queue as a 250 MW solar project in Reeves County, TX. The filing names Tap Verhalen – Hoefs Road as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of June 27, 2028. It records the screening study as complete on December 13, 2022 and the interconnection agreement as signed on September 12, 2025.
| Queue ID | 25INR0112 |
|---|---|
| Project name | August Draw Solar |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Tap Verhalen – Hoefs Road |
| Point of interconnection | Tap 138kV 60207 Verhalen – 60808 Hoefs Road |
| County | Reeves |
| State | TX |
| Voltage | 138 kV |
| Capacity | 250 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-06-27 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Reeves, TX: 27 requests in the ERCOT queue, 24 active totaling 8,349.7 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | August Draw Solar Holdings, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | SOL |
| Technology code | PV |
| Interconnection agreement signed | 2025-09-12 |
| Screening study complete | 2022-12-13 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.