August Draw Solar

ERCOT queue ID 25INR0112

August Draw Solar (25INR0112) is listed in the ERCOT interconnection queue as a 250 MW solar project in Reeves County, TX. The filing names Tap Verhalen – Hoefs Road as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of June 27, 2028. It records the screening study as complete on December 13, 2022 and the interconnection agreement as signed on September 12, 2025.

Queue ID25INR0112
Project nameAugust Draw Solar
Status (as published)SS Completed, FIS Started, IA
SubstationTap Verhalen – Hoefs Road
Point of interconnectionTap 138kV 60207 Verhalen – 60808 Hoefs Road
CountyReeves
StateTX
Voltage138 kV
Capacity250 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-06-27
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Reeves, TX: 27 requests in the ERCOT queue, 24 active totaling 8,349.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityAugust Draw Solar Holdings, LLC
CDR reporting zoneWEST
Fuel codeSOL
Technology codePV
Interconnection agreement signed2025-09-12
Screening study complete2022-12-13
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.