Findley Solar

ERCOT queue ID 25INR0021

Queue ID25INR0021
Project nameFindley Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap #107 Prairie Hill - #99 Ben Hur
Point of interconnectionTap 69kV #107 Prairie Hill - #99 Ben Hur
CountyLimestone
StateTX
Voltage69 kV
Capacity50.3 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-01-01
Source datasetlarge

Additional filed fields

Interconnecting EntityAdon Texas Sixteen LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete44540
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.