Substation Scout

Tap #107 Prairie Hill - #99 Ben Hur substation interconnection queue

2 active projects totalling 102 MW in the ERCOT queue.

2active projects
102active MW
2total filed
Queue IDProjectkVMWResourceStatus
28INR0048 Findley BESS 69 51.7 Battery SS Completed, FIS Completed, No IA
25INR0021 Findley Solar 69 50.3 Solar SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.