BasRanch (TEF - Due Diligence)

ERCOT queue ID 25INR0008

BasRanch (TEF - Due Diligence) (25INR0008) is listed in the ERCOT interconnection queue as a 1,350 MW gas project in Ward County, TX. The filing names tap Riverton Switch - Sand Lake Switch as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 1, 2028. It records the screening study as complete on November 2, 2020, the full interconnection study as approved on May 5, 2025 and the interconnection agreement as signed on July 16, 2025.

Queue ID25INR0008
Project nameBasRanch (TEF - Due Diligence)
Status (as published)SS Completed, FIS Completed, IA
Substationtap Riverton Switch - Sand Lake Switch
Point of interconnectiontap 345kV Riverton Switch - Sand Lake Switch
CountyWard
StateTX
Voltage345 kV
Capacity1,350 MW
Resource (as published)GAS/CC
Resource categoryGas (normalized for filtering)
Target commercial operation2028-12-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Ward, TX: 13 requests in the ERCOT queue, 12 active totaling 3,247.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityCPV Basin Ranch, LLC
CDR reporting zoneWEST
Fuel codeGAS
Technology codeCC
Interconnection agreement signed2025-07-16
Screening study complete2020-11-02
Full interconnection study approved2025-05-05
Air permit2024-11-25
Water availability2025-09-05

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first