Barcelona TxHSR TPSS HN-4
ERCOT queue ID 25INR0002
Barcelona TxHSR TPSS HN-4 (25INR0002) is listed in the ERCOT interconnection queue as a 50 MW project in Harris County, TX. The filing names tap HocklyC - Peters as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of July 15, 2028. It records the screening study as complete on April 17, 2019.
| Queue ID | 25INR0002 |
|---|---|
| Project name | Barcelona TxHSR TPSS HN-4 |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | tap HocklyC - Peters |
| Point of interconnection | tap 138kV 45885 HocklyC - 46220 Peters |
| County | Harris |
| State | TX |
| Voltage | 138 kV |
| Capacity | 50 MW |
| Resource (as published) | OTH/OT |
| Resource category | Other (normalized for filtering) |
| Target commercial operation | 2028-07-15 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Texas Central Rail Holdings, LLC |
|---|---|
| CDR reporting zone | HOUSTON |
| Fuel code | OTH |
| Technology code | OT |
| Screening study complete | 2019-04-17 |
| Air permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.