Kegans BESS (Houston IV BESS)

ERCOT queue ID 24INR0584

Kegans BESS (Houston IV BESS) (24INR0584) is listed in the ERCOT interconnection queue as a 164.6 MW battery project in Harris County, TX. The filing names CLODINE as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of September 5, 2026. It records the screening study as complete on October 5, 2023, the full interconnection study as approved on July 1, 2025 and the interconnection agreement as signed on November 7, 2024.

Queue ID24INR0584
Project nameKegans BESS (Houston IV BESS)
Status (as published)SS Completed, FIS Completed, IA
SubstationCLODINE
Point of interconnection44140 CLODINE 138kV
CountyHarris
StateTX
Voltage138 kV
Capacity164.6 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2026-09-05
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entitySMT Houston IV LLC
CDR reporting zoneHOUSTON
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2024-11-07
Screening study complete2023-10-05
Full interconnection study approved2025-07-01
Air permitNot Required
Water availability2025-09-18

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.