Substation Scout

Megacharge BESS

ERCOT queue ID 24INR0572

Megacharge BESS (24INR0572) is listed in the ERCOT interconnection queue as a 110 MW battery project in Cameron County, TX. The filing names WEST HARLINGEN as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of July 1, 2028. It records the screening study as complete on September 20, 2023.

Queue ID24INR0572
Project nameMegacharge BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationWEST HARLINGEN
Point of interconnection8320 WEST HARLINGEN 69kV
CountyCameron
StateTX
Voltage69 kV
Capacity110 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-07-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Cameron, TX: 32 requests in the ERCOT queue, 30 active totaling 8,649.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entitySMT Harlingen III LLC
CDR reporting zoneCOASTAL
Fuel codeOTH
Technology codeBA
Screening study complete2023-09-20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first