Kinney County Energy

ERCOT queue ID 24INR0541

Queue ID24INR0541
Project nameKinney County Energy
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Brackett4A - L_PINTCR8_1Y
Point of interconnectionTap 138kV 8252 Brackett4A - 78255 L_PINTCR8_1Y
CountyKinney
StateTX
Voltage138 kV
Capacity101.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-05-15
Source datasetlarge

Additional filed fields

Interconnecting EntityKinney County Energy, LLC
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45096