Kinney, TX interconnection queue

13 active projects totalling 1,459.7 MW in the ERCOT queue.

13active projects
1,459.7active MW
13total filed
Queue IDProjectkVMWResourceStatus
24INR0182 DeSpain Solar Project 138 236.2 Solar SS Completed, FIS Started, No IA
25INR0501 Longday Solar SLF 138 200.8 Solar SS Completed, FIS Started, No IA
26INR0448 Cairos Storage 2 138 184 Battery SS Completed, FIS Started, No IA
25INR0622 Turkey Creek Solar SLF 138 180.9 Solar SS Completed, FIS Started, No IA
26INR0246 Cairos Solar n/r 153.3 Solar SS Completed, FIS Started, No IA
29INR0251 Sugarberry Solar SLF 138 125 Solar SS Completed, FIS Started, No IA
24INR0541 Kinney County Energy 138 101.2 Battery SS Completed, FIS Started, No IA
23INR0284 Las Moras Battery 138 101 Battery SS Completed, FIS Started, No IA
23INR0204 GALVANIC BESS 138 100 Battery SS Completed, FIS Started, No IA
26INR0245 Cairos Storage 138 77.3 Battery SS Completed, FIS Started, No IA
25INR0502 Longday BESS SLF 138 0 Battery SS Completed, FIS Started, No IA
25INR0623 Turkey Creek Battery Energy Storage System SLF 138 0 Battery SS Completed, FIS Started, No IA
29INR0252 Sugarberry Storage SLF 138 0 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.