ERCOT queue ID 24INR0534
| Queue ID | 24INR0534 |
|---|---|
| Project name | Lyford Energy |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | E Raymondville |
| Point of interconnection | 5745 E Raymondville 138kV |
| County | Willacy |
| State | TX |
| Voltage | 138 kV |
| Capacity | 101.2 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2027-09-02 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Lyford Energy, LLC |
|---|---|
| Cdr Zone | COASTAL |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 45082 |