Substation Scout

Southside Energy

ERCOT queue ID 24INR0530

Queue ID24INR0530
Project nameSouthside Energy
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Mustang Bayou - HUDSON ckt 4
Point of interconnectionTap 138kV 42960 Mustang Bayou - 42100 HUDSON ckt 4
CountyBrazoria
StateTX
Voltage138 kV
Capacity101.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntitySouthside Energy, LLC
Cdr ZoneCOASTAL
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45072

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.