Claire BESS
ERCOT queue ID 24INR0500
| Queue ID | 24INR0500 |
|---|---|
| Project name | Claire BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Cedar Bayou |
| Point of interconnection | 40011 Cedar Bayou 138kV |
| County | Harris |
| State | TX |
| Voltage | 138 kV |
| Capacity | 406 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2027-12-17 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | BRP Blue Topaz 3, LLC |
|---|---|
| Cdr Zone | HOUSTON |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 45054 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.