High Plains Storage (24INR0419) is listed in the ERCOT interconnection queue as a 157.7 MW battery project in Harris County, TX. The filing names Hockley as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of May 30, 2029. It records the screening study as complete on November 29, 2022.

Queue ID24INR0419
Project nameHigh Plains Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationHockley
Point of interconnection45880 Hockley 138kV
CountyHarris
StateTX
Voltage138 kV
Capacity157.7 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2029-05-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityROBP Holdings, LLC
CDR reporting zoneHOUSTON
Fuel codeOTH
Technology codeBA
Screening study complete2022-11-29
Air permitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.