GIGA AUSTIN SOLAR
ERCOT queue ID 24INR0372
| Queue ID | 24INR0372 |
|---|---|
| Project name | GIGA AUSTIN SOLAR |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | HORNSBY Substation |
| Point of interconnection | 7047 HORNSBY Substation 138kV |
| County | Travis |
| State | TX |
| Voltage | 138 kV |
| Capacity | -53.3 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2027-03-14 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | GIGA TEXAS ENERGY LLC |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Screening Study Complete | 44848 |
| Water Availability | Not Required |