Substation Scout

Travis, TX interconnection queue

8 active projects totalling 631.9 MW in the ERCOT queue.

8active projects
631.9active MW
8total filed
Queue IDProjectkVMWResourceStatus
25INR0688 Giga Texas Data Center 24.9 133 Battery SS Completed, FIS Completed, IA
27INR0485 Blackland Prairie 1 Energy Storage 138 102.1 Battery SS Completed, FIS Started, IA
27INR0486 Blackland Prairie 2 Energy Storage 138 102.1 Battery SS Completed, FIS Started, No IA
27INR0487 Blackland Prairie 3 Energy Storage 138 102.1 Battery SS Completed, FIS Started, No IA
23INR0474 AP Greenport 345 100.5 Battery SS Completed, FIS Completed, No IA
25INR0266 East Blackland Battery Storage SLF 138 75 Battery SS Completed, FIS Started, No IA
22INR0488 Venture Hill Storage 138 70.4 Battery SS Completed, FIS Started, No IA
24INR0372 GIGA AUSTIN SOLAR 138 -53.3 Solar SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.