Substation Scout

Citrus Flatts BESS

ERCOT queue ID 24INR0294

Queue ID24INR0294
Project nameCitrus Flatts BESS
Status (as published)SS Completed, FIS Completed, IA
SubstationOleander
Point of interconnection80022 Oleander 138kV
CountyCameron
StateTX
Voltage138 kV
Capacity103 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-07-29
Source datasetlarge

Additional filed fields

Interconnecting EntityCitrus Flatts Energy Center, LLC
Cdr ZoneCOASTAL
Fuel CodeOTH
Technology CodeBA
Ia Signed45177
Screening Study Complete44738
Fis Approved45708
Air PermitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.