Citrus Flatts BESS
ERCOT queue ID 24INR0294
| Queue ID | 24INR0294 |
|---|---|
| Project name | Citrus Flatts BESS |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Oleander |
| Point of interconnection | 80022 Oleander 138kV |
| County | Cameron |
| State | TX |
| Voltage | 138 kV |
| Capacity | 103 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2026-07-29 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Citrus Flatts Energy Center, LLC |
|---|---|
| Cdr Zone | COASTAL |
| Fuel Code | OTH |
| Technology Code | BA |
| Ia Signed | 45177 |
| Screening Study Complete | 44738 |
| Fis Approved | 45708 |
| Air Permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.