Substation Scout

Rockridge Solar

ERCOT queue ID 24INR0287

Queue ID24INR0287
Project nameRockridge Solar
Status (as published)SS Completed, FIS Started, IA
SubstationHickory Forest
Point of interconnection7225 Hickory Forest 138kV
CountyGuadalupe
StateTX
Voltage138 kV
Capacity211.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-06-27
Source datasetlarge

Additional filed fields

Interconnecting EntityMagnolia Solar Development, LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Ia Signed45730
Screening Study Complete44754
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.