Rockridge Solar
ERCOT queue ID 24INR0287
| Queue ID | 24INR0287 |
|---|---|
| Project name | Rockridge Solar |
| Status (as published) | SS Completed, FIS Started, IA |
| Substation | Hickory Forest |
| Point of interconnection | 7225 Hickory Forest 138kV |
| County | Guadalupe |
| State | TX |
| Voltage | 138 kV |
| Capacity | 211.2 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-06-27 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Magnolia Solar Development, LLC |
|---|---|
| Cdr Zone | SOUTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Ia Signed | 45730 |
| Screening Study Complete | 44754 |
| Air Permit | Not Required |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.