Substation Scout

Kennedy Solar

ERCOT queue ID 24INR0256

Kennedy Solar (24INR0256) is listed in the ERCOT interconnection queue as a 101.5 MW solar project in Navarro County, TX. The filing names Tap Kopprl Capacitor Yard - Navarro as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 31, 2028. It records the screening study as complete on June 2, 2022.

Queue ID24INR0256
Project nameKennedy Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Kopprl Capacitor Yard - Navarro
Point of interconnectionTap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro
CountyNavarro
StateTX
Voltage345 kV
Capacity101.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap Kopprl Capacitor Yard - Navarro substation: 2 requests in the ERCOT queue, 2 active totaling 126.8 MW.

Queue IDProjectMWResourceStatus
24INR0391Kennedy Storage25.3BatterySS Completed, FIS Started, No IA

Navarro, TX: 29 requests in the ERCOT queue, 26 active totaling 4,412.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityKennedy Bypass Solar LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Screening study complete2022-06-02
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.