ERCOT queue ID 24INR0256

Queue ID24INR0256
Project nameKennedy Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Kopprl Capacitor Yard - Navarro
Point of interconnectionTap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro
CountyNavarro
StateTX
Voltage345 kV
Capacity101.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityKennedy Bypass Solar LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete44714
Water AvailabilityNot Required