Substation Scout

SANJAC BESS

ERCOT queue ID 24INR0081

SANJAC BESS (24INR0081) is listed in the ERCOT interconnection queue as a 202.4 MW battery project in Harris County, TX. The filing names Riverside as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 4, 2027. It records the screening study as complete on September 28, 2021.

Queue ID24INR0081
Project nameSANJAC BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationRiverside
Point of interconnection40270 Riverside 138kV
CountyHarris
StateTX
Voltage138 kV
Capacity202.4 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2027-04-04
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityCastleman Power
CDR reporting zoneHOUSTON
Fuel codeOTH
Technology codeBA
Screening study complete2021-09-28

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first