Substation Scout

Soda Lake BESS 1

ERCOT queue ID 23INR0501

Soda Lake BESS 1 (23INR0501) is listed in the ERCOT interconnection queue as a 203.9 MW battery project in Crane County, TX. The filing names Soda Lake Substation (#) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of August 15, 2026. It records the screening study as complete on November 29, 2022, the full interconnection study as approved on October 22, 2024 and the interconnection agreement as signed on August 20, 2018.

Queue ID23INR0501
Project nameSoda Lake BESS 1
Status (as published)SS Completed, FIS Completed, IA
SubstationSoda Lake Substation (#)
Point of interconnection138kV Soda Lake Substation (#76026)
CountyCrane
StateTX
Voltage138 kV
Capacity203.9 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2026-08-15
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Crane, TX: 14 requests in the ERCOT queue, 13 active totaling 2,944.5 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityMendoza Trail BESS, LLC
CDR reporting zoneWEST
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2018-08-20
Screening study complete2022-11-29
Full interconnection study approved2024-10-22
Air permitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first