Soda Lake BESS 1
ERCOT queue ID 23INR0501
Soda Lake BESS 1 (23INR0501) is listed in the ERCOT interconnection queue as a 203.9 MW battery project in Crane County, TX. The filing names Soda Lake Substation (#) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of August 15, 2026. It records the screening study as complete on November 29, 2022, the full interconnection study as approved on October 22, 2024 and the interconnection agreement as signed on August 20, 2018.
| Queue ID | 23INR0501 |
|---|---|
| Project name | Soda Lake BESS 1 |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Soda Lake Substation (#) |
| Point of interconnection | 138kV Soda Lake Substation (#76026) |
| County | Crane |
| State | TX |
| Voltage | 138 kV |
| Capacity | 203.9 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2026-08-15 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Crane, TX: 14 requests in the ERCOT queue, 13 active totaling 2,944.5 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Mendoza Trail BESS, LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2018-08-20 |
| Screening study complete | 2022-11-29 |
| Full interconnection study approved | 2024-10-22 |
| Air permit | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.