Substation Scout

Lumen Farm Solar SLF

ERCOT queue ID 23INR0439

Lumen Farm Solar SLF (23INR0439) is listed in the ERCOT interconnection queue as a 201 MW solar project in Anderson County, TX. The filing names Tap Blackburn Switch – Palestine as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 30, 2028. It records the screening study as complete on March 31, 2022.

Queue ID23INR0439
Project nameLumen Farm Solar SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Blackburn Switch – Palestine
Point of interconnectionTap 138kV 3325 Blackburn Switch – 3272 Palestine
CountyAnderson
StateTX
Voltage138 kV
Capacity201 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2028-09-30
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap Blackburn Switch – Palestine substation: 2 requests in the ERCOT queue, 2 active totaling 201 MW.

Queue IDProjectMWResourceStatus
24INR0450Lumen Farm BESS SLF0BatterySS Completed, FIS Started, No IA

Anderson, TX: 9 requests in the ERCOT queue, 9 active totaling 4,644.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityNeches Solar, LLC
CDR reporting zoneNORTH
Fuel codeSOL
Technology codePV
Screening study complete2022-03-31
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first