Rocking X Solar
ERCOT queue ID 23INR0368
Rocking X Solar (23INR0368) is listed in the ERCOT interconnection queue as a 602.2 MW solar project in Parker County, TX. The filing names Tap the Parker Switch (bus#) – Comanche Peak SES (bus#) Double-Circuit line, Circuit 1. as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of September 20, 2027. It records the screening study as complete on December 19, 2023.
| Queue ID | 23INR0368 |
|---|---|
| Project name | Rocking X Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap the Parker Switch (bus#) – Comanche Peak SES (bus#) Double-Circuit line, Circuit 1. |
| Point of interconnection | Tap the 345 kV Parker Switch (bus#1436) – Comanche Peak SES (bus#1900) Double-Circuit line, Circuit 1. |
| County | Parker |
| State | TX |
| Voltage | 345 kV |
| Capacity | 602.2 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-09-20 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Parker, TX: 4 requests in the ERCOT queue, 4 active totaling 2,222.2 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | 7100 Tin Top LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | SOL |
| Technology code | PV |
| Screening study complete | 2023-12-19 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.