Substation Scout

Brizo BESS

ERCOT queue ID 23INR0342

Brizo BESS (23INR0342) is listed in the ERCOT interconnection queue as a 144.2 MW battery project in Victoria County, TX. The filing names Loop 463 Substation (#) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of September 1, 2027. It records the screening study as complete on December 22, 2021 and the interconnection agreement as signed on March 27, 2025.

Queue ID23INR0342
Project nameBrizo BESS
Status (as published)SS Completed, FIS Started, IA
SubstationLoop 463 Substation (#)
Point of interconnection138 kV Loop 463 Substation (#5680)
CountyVictoria
StateTX
Voltage138 kV
Capacity144.2 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2027-09-01
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Victoria, TX: 22 requests in the ERCOT queue, 17 active totaling 5,382.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityBRP Brizo BESS LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2025-03-27
Screening study complete2021-12-22
Air permitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first