Hanson Solar

ERCOT queue ID 23INR0086

Hanson Solar (23INR0086) is listed in the ERCOT interconnection queue as a 398.8 MW solar project in Coleman County, TX. The filing names tap Brown - Central Bluff as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of August 17, 2027. It records the screening study as complete on February 2, 2021, the full interconnection study as approved on March 26, 2026 and the interconnection agreement as signed on September 20, 2023.

Queue ID23INR0086
Project nameHanson Solar
Status (as published)SS Completed, FIS Completed, IA
Substationtap Brown - Central Bluff
Point of interconnectiontap 345kV 1444 Brown - 11406 Central Bluff
CountyColeman
StateTX
Voltage345 kV
Capacity398.8 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-08-17
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Coleman, TX: 9 requests in the ERCOT queue, 7 active totaling 1,746.6 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityHanson Solar, LLC
CDR reporting zoneWEST
Fuel codeSOL
Technology codePV
Interconnection agreement signed2023-09-20
Screening study complete2021-02-02
Full interconnection study approved2026-03-26
Air permitNot Required
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.