BRP Ampato BESS
ERCOT queue ID 23INR0074
BRP Ampato BESS (23INR0074) is listed in the ERCOT interconnection queue as a 121.6 MW battery project in Crane County, TX. The filing names NS Crane Switch as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of December 1, 2027. It records the screening study as complete on October 28, 2020.
| Queue ID | 23INR0074 |
|---|---|
| Project name | BRP Ampato BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | NS Crane Switch |
| Point of interconnection | 10002 NS Crane Switch 138kV |
| County | Crane |
| State | TX |
| Voltage | 138 kV |
| Capacity | 121.6 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2027-12-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Crane, TX: 14 requests in the ERCOT queue, 13 active totaling 2,944.5 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | BRP Ampato BESS LLC |
|---|---|
| CDR reporting zone | WEST |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2020-10-28 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.