Accalia Point Solar

ERCOT queue ID 23INR0066

Accalia Point Solar (23INR0066) is listed in the ERCOT interconnection queue as a 190.5 MW solar project in Cameron County, TX. The filing names Tap North Edingburg – Kingfisher as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of May 31, 2029. It records the screening study as complete on January 12, 2021.

Queue ID23INR0066
Project nameAccalia Point Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap North Edingburg – Kingfisher
Point of interconnectionTap 345kV 8383 North Edingburg – 79501 Kingfisher
CountyCameron
StateTX
Voltage345 kV
Capacity190.5 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2029-05-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Cameron, TX: 32 requests in the ERCOT queue, 30 active totaling 8,649.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityAccalia Point Solar LLC
CDR reporting zoneCOASTAL
Fuel codeSOL
Technology codePV
Screening study complete2021-01-12
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.