Callisto II Energy Center
ERCOT queue ID 22INR0558
Callisto II Energy Center (22INR0558) is listed in the ERCOT interconnection queue as a 203.2 MW battery project in Harris County, TX. The filing names HO Clarke as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of December 17, 2026. It records the screening study as complete on December 8, 2021, the full interconnection study as approved on August 21, 2025 and the interconnection agreement as signed on December 11, 2023.
| Queue ID | 22INR0558 |
|---|---|
| Project name | Callisto II Energy Center |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | HO Clarke |
| Point of interconnection | 47150 HO Clarke 138kV |
| County | Harris |
| State | TX |
| Voltage | 138 kV |
| Capacity | 203.2 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2026-12-17 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Callisto II Energy Center LLC |
|---|---|
| CDR reporting zone | HOUSTON |
| Fuel code | OTH |
| Technology code | BA |
| Interconnection agreement signed | 2023-12-11 |
| Screening study complete | 2021-12-08 |
| Full interconnection study approved | 2025-08-21 |
| Air permit | Not Required |
| Water availability | 2025-10-22 |