Enchanted Rock NEWPP (22INR0546) is listed in the ERCOT interconnection queue as a 30 MW gas project in Harris County, TX. The filing names Deusen as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of February 28, 2026. It records the screening study as complete on January 17, 2022, the full interconnection study as approved on April 19, 2024 and the interconnection agreement as signed on April 30, 2024.
| Queue ID | 22INR0546 |
|---|---|
| Project name | Enchanted Rock NEWPP |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Deusen |
| Point of interconnection | 40475 Deusen 138kV |
| County | Harris |
| State | TX |
| Voltage | 138 kV |
| Capacity | 30 MW |
| Resource (as published) | GAS/IC |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2026-02-28 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Generate ER-NG, LLC |
|---|---|
| CDR reporting zone | HOUSTON |
| Fuel code | GAS |
| Technology code | IC |
| Interconnection agreement signed | 2024-04-30 |
| Screening study complete | 2022-01-17 |
| Full interconnection study approved | 2024-04-19 |
| Air permit | 2024-04-25 |
| Water availability | 2024-04-30 |