Enchanted Rock NEWPP (22INR0546) is listed in the ERCOT interconnection queue as a 30 MW gas project in Harris County, TX. The filing names Deusen as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of February 28, 2026. It records the screening study as complete on January 17, 2022, the full interconnection study as approved on April 19, 2024 and the interconnection agreement as signed on April 30, 2024.

Queue ID22INR0546
Project nameEnchanted Rock NEWPP
Status (as published)SS Completed, FIS Completed, IA
SubstationDeusen
Point of interconnection40475 Deusen 138kV
CountyHarris
StateTX
Voltage138 kV
Capacity30 MW
Resource (as published)GAS/IC
Resource categoryGas (normalized for filtering)
Target commercial operation2026-02-28
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Harris, TX: 35 requests in the ERCOT queue, 30 active totaling 6,536.2 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityGenerate ER-NG, LLC
CDR reporting zoneHOUSTON
Fuel codeGAS
Technology codeIC
Interconnection agreement signed2024-04-30
Screening study complete2022-01-17
Full interconnection study approved2024-04-19
Air permit2024-04-25
Water availability2024-04-30

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.