BRP Kabru BESS
ERCOT queue ID 22INR0427
| Queue ID | 22INR0427 |
|---|---|
| Project name | BRP Kabru BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Andrew North - Blackbird |
| Point of interconnection | 1159 Andrew North - 11284 Blackbird 138kV |
| County | Andrews |
| State | TX |
| Voltage | 138 kV |
| Capacity | 202.5 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2028-12-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | BRP Kabru BESS LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 44193 |