Andrews, TX interconnection queue
9 active projects totalling 2,211.3 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).
9active projects
2,211.3active MW
10total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 30INR0135 | Blue Sage Wind | 345 | 394.1 | Wind | SS Started, FIS Started, No IA |
| 27INR0386 | Straight Spur Storage | 345 | 306.2 | Battery | SS Completed, FIS Started, No IA |
| 27INR0385 | Straight Spur Solar | 345 | 251.8 | Solar | SS Completed, FIS Started, No IA |
| 27INR0384 | Straight Spur Wind | 345 | 247.4 | Wind | SS Completed, FIS Started, No IA |
| 23INR0279 | Trivor BESS | 138 | 205.5 | Battery | SS Completed, FIS Started, No IA |
| 23INR0104 | BRP Kamet BESS | 138 | 202.5 | Battery | SS Completed, FIS Started, No IA |
| 22INR0427 | BRP Kabru BESS | 138 | 202.5 | Battery | SS Completed, FIS Started, No IA |
| 23INR0278 | Tucana BESS | 138 | 201.3 | Battery | SS Completed, FIS Completed, No IA |
| 19INR0103 | Rodeo Solar | 138 | 200 | Solar | SS Completed, FIS Started, IA |
| 20INR0096 | Desert Rose Solar | n/r | 200 | Solar | Inactive |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.