Substation Scout

Blue Jay Solar II

ERCOT queue ID 21INR0538

Queue ID21INR0538
Project nameBlue Jay Solar II
Status (as published)SS Completed, FIS Completed, IA
Substation4 Iola
Point of interconnection4 Iola 138kV
CountyGrimes
StateTX
Voltage138 kV
Capacity69 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2025-10-31
Source datasetlarge

Additional filed fields

Interconnecting EntityBlue Jay Solar I, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Ia Signed44130
Screening Study Complete44300
Fis Approved44312
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.